Results
Days recovered, delay proven, money released.
Real outcomes from mechanical recovery work. Client names stay confidential under NDA.
113 days of delay recovered
- Problem
- A specialty valve gap scope delayed the mechanical work.
- What we did
- Documented the delay and what caused it.
- Result
- 113 days recovered as extended general conditions through a change order.
Time extension granted through a TIA
- Problem
- Clash coordination was never signed off between the core & shell and fit-up construction managers, so underground stub-ups could not proceed until locations were verified.
- What we did
- Built a Time Impact Analysis that tied the late sign-off to the critical path.
- Result
- Time extension granted.
Free project health check
Every day of delay is on the clock.
Tell us what’s going on. After you submit, you’ll pick a time for a free 30-minute call with Timmy.
- Schedule slipping or negative float
- Liquidated damages exposure
- Rejected change orders or labor overruns
- Stalled test packages or commissioning
- Retainage stuck at closeout
What happens next
- Fill in the form (about 3 minutes).
- Pick a time for a free 30-minute call with Timmy.
- Get a follow-up email with what we found, your options, and pricing if you want help.
Form not loading? Open it in a new tab.
Free: the LD Defense Kit
4 checklists that stop the most common causes of late mechanical turnover.